| PANEL INSTALLATION GUIDE
TOC > BEFORE YOU START >
WALL PANELS > 2ND PANEL
How to Work with Wall Panels
Continue with your second, and additional panels
around the wall. All panel to panel joints that dont fall
over a timber must be splined together. Study Figure 11. Slip
splines into the spline channels as you go. If you use panel pieces,
you may have to create these channels with the hot knife. Be careful
to keep up with this! Splines will be hard to insert between panels
from the top if you have more than a 10 tall panel. Its
almost impossible to get splines in after very tall panels (10
to 16) are all up, so insert splines as you go!

Figure 11. Install your splines as you go
> PAY ATTENTION
TO THE PANEL LAYOUT
|